South Carolina Ports Halts Construction to Clear Vessel Backlog

This collaboration with maritime partners has led to decreased wait times and fewer anchored ships


South Carolina Ports (SC Ports) is addressing a ship backlog caused by a two-day software issue in May and ongoing berth impacts at Wando Welch Terminal. The company has temporarily stopped construction work and is making progress in reducing ship delays and improving port operations. Collaboration with maritime partners has decreased wait times and reduced the number of ships anchored, currently standing at three.

The toe wall construction, which began in March 2024, is essential for maintaining a 54-foot berth depth but has resulted in delays due to limited berth availability. SC Ports will pause construction from July 3 to July 14, reopening all three berths at Wando Welch Terminal to expedite ship processing and clear the backlog. By mid-July, SC Ports expects to handle ships upon arrival, although a 48-hour average wait is anticipated when construction resumes in August.

“Our SC Ports team and maritime partners are working together to ensure fluidity for our customers amid this critical infrastructure project,” said SC Ports President and CEO Barbara Melvin. “Our ability to provide creative solutions when challenges arise, along with the incredible support we receive from our customers, makes all the difference in navigating short-term supply chain challenges.”

News of the collaboration comes just a week after SC Ports and the International Longshoremen’s Association (ILA) reached an agreement to reopen the Hugh K. Leatherman Terminal in Charleston after months of intense negotiations, This terminal, which originally opened in March 2021, had been largely inactive due to a protracted dispute over crane operations between the two entities.

SC Ports has implemented several operational measures to mitigate delays, including extended working hours with start times throughout the night and early morning, flexible terminal calls between Wando Welch and North Charleston, and virtual queue times to communicate estimated berthing times to ocean carriers. These measures have been well-received by ocean carrier partners and cargo customers, restoring regular calls and services.

Looking ahead, SC Ports plans to work three ships simultaneously at Wando Welch Terminal by late fall, ahead of the project's scheduled completion in March 2025. The planned reopening of Leatherman Terminal will also provide an additional berth for ocean carriers at the Port of Charleston, further enhancing port capacity and efficiency.

“Our ocean carrier partners are seeing positive effects from the measures we have implemented, and cargo customers appreciate the restoration of regular calls and services,” said SC Ports’ Chief Commercial Officer Byron Miller. “We have proactively worked with our ocean carrier customers, maritime partners, and logistics providers to provide solutions. We appreciate the confidence, support, and encouragement from our customers as we navigate these challenges. We will continue delivering the superior service they have come to expect from us.”


Article Topics


SC Ports News & Resources

South Carolina Ports Halts Construction to Clear Vessel Backlog
Charleston’s Leatherman Terminal to Reopen After Long Dispute

Latest in Supply Chain

DOF Group to Acquire Maersk Supply Service in $1.1 Billion Deal
Why Companies Should Look to LLMs, Not Chatbots, For Their AI Needs
Retail Supply Chains Embrace AI to Improve ESG Compliance
Optilogic and GM Form Partnership to Improve Supply Chain Efficiency
Bellingham and San Diego Ports Secure Key RAISE Grants for Infrastructure
Ports of LA and Long Beach Commit $25M to Electric Truck Charging Sites
Coyne Airways First to Offer Dangerous Goods Booking via WebCargo
More Supply Chain
SC Ports has implemented several operational measures to mitigate delays including flexible terminal calls between Wando Welch and North Charleston.
Source: Courtesy of SCSPA
SC Ports has implemented several operational measures to mitigate delays including flexible terminal calls between Wando Welch and North Charleston.

 

Featured Downloads

Automation Revolution: Transforming Procurement for Strategic Impact
Automation Revolution: Transforming Procurement for Strategic Impact
Discover how strategic automation empowers procurement teams to navigate global supply chain challenges effectively, enhancing resilience and driving transformative business impact.
Navigating Procurement’s Digital Transformation with AI
Navigating Procurement’s Digital Transformation with AI
In today's rapidly evolving business landscape, the role of AI in reshaping procurement and supply chain operations is undeniable. This whitepaper by...

Unified Control System - Intelligent Warehouse Orchestration
Unified Control System - Intelligent Warehouse Orchestration
Download this whitepaper to learn Unified Control System (UCS), designed to orchestrate automated and human workflows across the warehouse, enabling automation technologies...
An Inside Look at Dropshipping
An Inside Look at Dropshipping
Korber Supply Chain’s introduction to the world of dropshipping. While dropshipping is not for every retailer or distributor, it does provide...
C3 Solutions Major Trends for Yard and Dock Management in 2024
C3 Solutions Major Trends for Yard and Dock Management in 2024
What trends you should be focusing on in 2024 depends on how far you are on your yard and dock management journey. This...